The Mall at Northgate is being rebuilt on two clocks. On the first, the former Sears came down this spring, a grocery has announced a spring 2027 opening, and the developer has set Spring 2029 as the target for housing construction, open-air shopping and a new town square. The second clock starts with demolishing Macy's and Kohl's, and the developer places its finish somewhere in an eleven-year window ending in 2040.
If you're looking at homes in Terra Linda near Northgate Drive or Las Gallinas Avenue, the second clock is the one to plan around. Phase 1 is the visible work, but it's also the part with a defined end. The open-ended part involves the mall's two largest remaining anchor buildings, and whether it falls during your ownership depends mostly on how long you plan to stay.
What was approved
In December 2024 the San Rafael City Council unanimously approved Northgate Town Square, as NorthBay Biz reported. The plan has 1,422 homes in six residential sections, 143 of them affordable, in buildings two to seven stories tall. A mid-2024 revision spread the affordable homes across the site and dropped the earlier plan for one standalone affordable building. It also added 138 townhomes, according to the Marin Independent Journal.
The revision also changed how the homes are split between phases. The city's Final EIR puts 864 homes in Phase 1 and 558 in Phase 2. Of the 143 affordable homes, 87 are in Phase 1 and 56 in Phase 2. That puts about 60 percent of the housing in the phase with the nearer target date.
Phase 1: the dated work
The EIR lists what Phase 1 removes: the RH Outlet building, the HomeGoods building and Mall Shops East, about 144,432 square feet of the main mall. The two vacant Sears buildings are also on the Phase 1 demolition list. The Marin IJ reported crews preparing the old Sears for demolition in February 2026 and tearing it down in May.
Phase 1 keeps and adds as well as removes. The Century Theatre stays and gets a roughly 20,000-square-foot addition. The plan adds four commercial pads: one sized for a sit-down restaurant at 8,400 square feet, one for a drive-through restaurant at 4,300 square feet, and two smaller retail pads. It also includes a San Rafael Police Department substation of about 200 square feet.
The open space matters most to people who live nearby. The revised Town Square grew from 48,075 to 56,975 square feet. Synthetic turf was swapped for natural turf, shade trees were added around the lawn, a larger playground went in along the north side, and the dog park shrank. The bike hub in front of the cinema is 9,604 square feet. At Northgate Drive and Las Gallinas Avenue, a bike rest stop gets a water fountain, benches, a dog waste dispenser and bike racks. The multi-use trail along Las Gallinas is planned to extend south to Northgate Drive.
The developer's project site, futurenorthgatemall.com, gives this stretch a window of Fall 2024 to Spring 2029. Its list for that window includes permits, the start of housing construction, the full change to open-air shopping and the opening of the town square. The developer numbers its stages differently from the EIR. On the developer's site, this construction window is called "Phase 2," and planning and approvals are its "Phase 1." In this post, Phase 1 and Phase 2 mean the physical phases in the city's EIR.
The first retail news is a grocery
The clearest sign of what the new Northgate will be like is a grocery store. In February, Good Earth Natural Foods announced a third store at 1500 Northgate, the freestanding former Rite Aid building near Macy's. The store will be about 21,300 square feet, and the company calls it an anchor tenant of the redeveloped mall. Its stated opening target is spring 2027. Good Earth's other stores are in Fairfax and at Tam Junction in Mill Valley, so this would be its first store in North San Rafael.
If you're weighing a house within walking or biking distance, a full-service grocery with a public lawn and playground next to it changes how the Northgate end of Terra Linda works day to day. It also shows that the first new anchor is an everyday errand rather than a destination store.
Phase 2: the undated work
Phase 2 starts by demolishing the 254,015-square-foot Macy's building, the 79,051-square-foot Kohl's building and Shops 1. New retail goes up in their place: two new major-tenant spaces, two shop spaces and three retail pads. Then come the remaining 558 homes.
The developer's site places this stage between Spring 2029 and 2040, describing it as the stretch when "all walking paths" get connected and the "second phase of housing" is finished. The EIR calls Phase 2 the "2040 Vision Plan." An eleven-year window isn't a construction schedule. Treat it as a range in which the largest demolition on the site could happen.
That's why a buyer's time horizon decides this. A household that buys this winter and plans to sell around 2031 or 2032 lives through Phase 1. If the developer's targets hold, that household probably sells into a neighborhood where the town square is open and Macy's and Kohl's are still operating. A household planning to stay 12 to 15 years should expect the Macy's and Kohl's demolition to fall somewhere in its ownership, followed by another round of building on the west side of the site. The EIR describes an open-space area of about 9,000 square feet west of the Macy's building in the earlier plan. On a map, the parts of the site that change last are the ones those two buildings sit on.
The longer you plan to own, the more you should judge a nearby house by what Northgate will be in 2040, and the less by what it is during the current construction.
More housing nearby, plus Freitas Parkway
Northgate Town Square isn't the only project on Northgate Drive. In April 2026 the city approved a separate 191-apartment complex at 555 Northgate Drive, according to the Marin IJ. The paper reported that Terra Linda residents said the neighborhood was taking on too much new housing and that traffic planning wasn't keeping up. Traffic was also the main concern in 2024, when residents commenting on the mall's draft environmental review raised traffic, noise and emergency access, as the Marin IJ reported that February.
Caltrans has done major work on the main route into the area. It scheduled the Manuel T. Freitas Roundabout and the Civic Center Drive and Redwood Highway intersection to open June 8, 2026. That intersection had been closed since February for the roundabout, a new bus stop and a northbound slip on-ramp. The roundabout is a Caltrans project with its own schedule and isn't part of the Northgate approval. If Freitas Parkway is your daily route to Highway 101, drive it at the hours you'd commute before you write an offer. The 2026 version of that drive is the one to judge.
The county market is tight
Right now the county market doesn't leave much room to wait for the mall to finish. In its October 2026 report, released November 17, the California Association of Realtors put Marin's median single-family sale price at $1,805,000, up 7.4 percent from October 2025. Median time on market in Marin was 52 days in October 2026, down from 59 a year earlier. Unsold inventory was 1.9 months, down from 2.4. C.A.R. also reported that Marin was the only California county where October sales were unchanged from a year earlier.
Those are countywide figures for detached homes. They don't show any Northgate effect in either direction. They do show that buyers in Marin this fall had less time and fewer choices than a year ago. In that market, the construction calendar is better used to decide which house fits your timeline than as a reason to expect a discount. For more on reading prices across North San Rafael, see our earlier post on the Terra Linda and Peacock Gap medians, and on our San Rafael neighborhood page.
FAQ
Will Macy's and Kohl's close during Phase 1? Under the approved plan, both buildings are demolished in Phase 2. The Century Theatre stays and gets an addition in Phase 1. Store leases are decided separately from the plan, so treat the phasing as a sequence of buildings, not a promise about which stores will be open.
When does the town square open? The developer's site includes the town square opening in its construction window running through Spring 2029.
What kinds of housing are planned? The approved plan includes 138 townhomes alongside apartment buildings. The 555 Northgate Drive project is a separate apartment complex.
If you're thinking about a home near Northgate, start with how long you plan to stay, then compare that against the Phase 1 and Phase 2 calendars house by house. A neighborhood orientation around the mall's edges, read against the phase map, is a practical first step, and it works in person or virtually. Staal Real Estate can help you schedule a consultation whenever you're ready.